The corner piece must be installed into the waterproofing system before the installation of the tape and membrane. Tile adhesive REDBAG 114 / 115 / 116 must be applied to the prepared surface in the external corner area and evenly spread with a trowel.
Then the corner piece should be installed into the fresh adhesive layer, firmly pressed to the substrate, and smoothed with a trowel so that the fleece part is fully saturated with adhesive. During installation, formation of folds, air pockets, and incomplete adhesion of the material to the surface must be avoided.
After installation of the corner piece, the waterproofing tape is applied with an overlap of at least 5 cm onto the corner piece. The tape must be fully embedded into the adhesive layer and ensure a watertight connection in the corner area.
Next, the waterproofing membrane is installed, overlapping the tape and corner pieces to form a continuous waterproof layer in accordance with the system technology.
All system elements must be fully bonded without voids or delamination. Installation of corner pieces in expansion joints is not permitted. The work must be carried out in accordance with the installation technology for waterproofing and tiling systems.