Work should be carried out at a base temperature of +5 °C to +30 °C. The prepared adhesive solution should be applied evenly to the horizontal and vertical surfaces of the blocks with a notched trowel or spatula in a layer of 2-6 mm. The adhesive solution should be applied to the entire horizontal surface without leaving free zones. The solution is applied to the vertical surface in a thin, even layer. The position of the aerated concrete block should be adjusted using a rubber mallet. After laying the aerated concrete block, remove any possible adhesive residue.
The shelf life of the mortar mixture is 2 hours. The blocks must be laid no later than 15 minutes from the moment of applying the adhesive solution. The block should be adjusted within 10 minutes. after its installation.
To fill the surface, the mortar mixture should be applied using a ladle and a stainless steel metal trowel and spread in an even continuous layer to the required thickness. The maximum layer thickness should not exceed 6 mm per application.